This week, our factory completed the dispatch of a 1 MWp ground mounting project in Sierra Leone. Dispatch Timeline July 1 - Production & QC Completed All structures for the 1 MWp project finished manufacturing. Our team conducted final quality control inspections on dimensions and anodized coatings. July 3, 2026 - Secure Packaging Components were carefully sorted, bundled, and strapped onto heavy-duty pallets to ensure zero damage during the long ocean transit to West Africa. July 5, 2026 - Container Loading & Dispatch Multiple containers were successfully loaded at our factory and dispatched to the port, ready for their journey to Sierra Leone.